Project Summary
Structured migration of an on-premises server estate to Microsoft Azure. Production infrastructure migration requiring controlled wave planning and coordinated client validation.
The engagement first established an Azure Landing Zone and assessed governance, hypervisor, VM, and network readiness, then deployed Azure Migrate, replication, and the required cloud network services.
Migration was organized into two controlled waves: 36 VMs including five SQL workloads, followed by 46 VMs, with each wave sequenced through source shutdown, Azure start-up, technical validation, backup enablement, and replication cleanup.
Project concluded with architecture/build documentation, Azure portal walkthrough, lessons learned, and project closeout.
Project Details
demonstrated capabilities
Azure and hybrid infrastructure, servers/virtualization, networking, migration-wave planning, production transition, client coordination, progress reporting, operational handover.